Amid complaints from Austria, Slovakia has decided to push back the long-awaited opening of two new nuclear reactors. Activists claim to have evidence that the reactors' safety structures are damaged and could fail.
Advertisement
Slovakian officials have announced a delay of their plans to expand Mochovce nuclear power plant and accused Vienna of trying to meddle with Bratislava's "sovereignty" on Monday.
The plant is located some 100 kilometers (62 miles) from Austria's border. For decades, Austria's politicians and activists have been trying to cancel the plans to add two more nuclear reactors to the facility, citing safety concerns. In April this year, environmental watchdog Global 2000 said construction had major flaws. They also cited photos and testimonies which allegedly showed the reactors' protective containment structure was damaged and could fail in case of an earthquake or a serious accident.
Another reason for concern is that the reactors were originally built to Soviet-style designs, and then modified with Western elements. The two new reactors were originally projected to start work in 2012 and 2013, but the project was repeatedly delayed.
Speaking to Slovak lawmakers on Monday, the CEO of state energy company Slovenske Elektrarne (SE) Branislav Strycek said the opening would be delayed once again, moving from June this year to at least November and possibly to March 2020. He said Austria's objections are the reason for the latest change.
Austria has been urging the International Atomic Energy Agency (IAEO) to send its experts to inspect the site. However, this will only happen if Slovakia invites the inspectors to the Mochovce plant.
Following the announcement on Monday, Austria's Chancellor Sebastian Kurz said it was a "step in the right direction."
"We will not let up until all our safety concerns have been answered," he was quoted by the Krone newspaper as saying.
Does nuclear power have a future?
On April 26, 1986, the Chernobyl disaster released radiation across Ukraine, Russia and into Europe. It was turning point for the anti-nuclear movement. Now, 31 years later, is nuclear power becoming a thing of the past?
Image: Kerry Skyring
Deadly disaster
The worst nuclear disaster of all time, the explosion at Chernobyl nuclear plant in Ukraine released massive amounts of radiation into the atmosphere. Areas close to the plant - in Ukraine, Belarus and Russia - were heavily contaminated. Heightened levels of radiation were also measured across most of Europe. The "exclusion zone" around Chernobyl remains off-limits to human habitation today.
Image: picture-alliance/ dpa
It happens again
After a magnitude-9 earthquake and consequent tsunami, three nuclear reactors at Fukushima power plant in Japan went into meltdown in March 2011. There were also four hydrogen explosions. The accident released 500 times as much radioactive cesium-137 as the nuclear bomb dropped on Hiroshima in 1945. The clean-up is expected to take decades.
Image: picture-alliance/dpa
Sickening impact
After Chernobyl, thousands of people developed cancer. In Japan too, the heavily contaminated region of Fukushima, where 200,000 people lost their homes, saw cases of the disease escalate. The number of children with thyroid cancer there is 20 times higher than other regions.
Image: Reuters
Rallying against nuclear power
Chernobyl fueled public opposition to nuclear power, particularly in Europe. The same happened after Fukushima. Before the Japanese disaster, the country relied on nuclear for 30 percent of its power. That has fallen to 1 percent. The government wants to continue producing nuclear power and plans to reinstall some reactors. But affected regions have successfully pushed back those plans.
Image: REUTERS
Nuclear industry in crisis
Today, the nuclear power sector is deep in economic crisis. In Japan, the United States and France, nuclear power plants run at a loss, and construction projects for new reactors have been postponed.
Image: Reuters
New-build set-backs
France had high hopes for its newest nuclear reactors - called pressurized water reactors (PWRs). This technology was supposed to be safe, and the Flamanville power plant was due to be switched on in 2012. Due to security issues, that's been pushed back to 2018 at the earliest. The project will cost more than 10 billion euros - three times the original budget.
Image: Getty Images/AFP/C. Triballeau
Great Britain plans new reactors
For years, the UK has been planning to build two new PWR reactors at Hinkley Point. Costs are estimated at 33 billion euros and groundbreaking is slated for 2019. But doubts are growing over its economic viability. The electricity it produces will be much pricier than solar or wind power, and will need subsidies to compete in the market.
Image: Getty Images/J. Tallis
Aging reactors up for grabs
Nuclear power plants used to be lucrative. But now, many are old and frail. Repair costs often mean they cannot turn a profit. Swiss energy corporation Alpiq recently tried to give away two of its old plants, 33 and 38 years old, to French energy company EDF - which declined the offer.
Image: picture-alliance/dpa/P. Seeger
Disasters abroad prompt German phase-out
Three decades ago, the Chernobyl disaster galvanized Germany's anti-nuclear movement, which is often cited as the roots of the country's energy transition. In 2002, Germany passed a law that would have seen the last reactor shut down in 2022. The plan was later scrapped by Angela Merkel's government. But after Fukushima, Merkel quickly reversed her decision and the phase-out was back on track.
Image: picture-alliance/dpa/D. Ebener
Switching them off
So far, nine of Germany's reactors have gone offline, with eight more to follow by 2022. To finance the costs of nuclear waste disposal, plant operators must pay 23.6 billion euros into a federal fund. The operators themselves are responsible for the similarly costly process of dismantling the plants, which will take decades to complete.
Image: picture-alliance/dpa/D. Ebener
Growing fear of accidents
Across the EU and Switzerland 132 nuclear reactors are still online. They were designed to operate for 30 to 35 years - their average age is now 32 years. Malfunctions and security issues are frequently detected and protestors are increasingly calling for plants to be shut down.
Image: DW/G. Rueter
China pushes on with nuclear
No new nuclear power plants have been built in the EU, Japan or Russia since the Fukushima disaster in 2011. China remains committed to nuclear, partly to replace coal-based power. But the country is also upping investment in wind and solar.
Image: Imago/China Foto Press
12 images1 | 12
Austria's 'holy war' on nuclear plants
However, Kurz faced sharp criticism from his Slovak counterpart, Prime Minister Peter Pellegrini, over the issue. Pellegrini slammed Austria for "declaring a holy war" against all nuclear power plants in the region.
The Slovakian leader also emphasized that his country has had decades of experience with nuclear power and that only Bratislava would decide on expanding its capacities.
Chancellor Kurz "is stepping over his competencies and attempting to meddle with the sovereignty and decision making of the Slovak Republic," Pellegrini said, according to Austria's public broadcaster ORF.
The two politicians are expected to discuss the issue at a Thursday EU summit in Romania's Sibiu.